Facilities Improvement Program: Recent Projects

Student and Staff Safety are of the Highest Importance to Ensure an Environment that Cultivates Learning and Growth.

Student and staff safety are of the highest importance to ensure an environment that cultivates learning and growth.   In a joint effort between the Town of South Kingstown and the South Kingstown School Department, the schools have been the focus of a Safe, Secure and Healthy Schools Project.  This Project is managed by the South Kingstown School Department and advised by the South Kingstown School Building Committee.  (The agendas and minutes are available on the South Kingstown School Building Committee here: https://clerkshq.com//Content/SouthKingstown-ri/Boards/SchoolBldg.htm  )
_______________________________________________________________

FALL 2019 & SUMMER 2020 SKSD PROJECT OVERVIEW
__________________________________________________


SAFE, SECURE & HEALTHY SCHOOLS: Parking Lot
SUMMER 2020

IMPORTANT UPDATE: This project is taking place during summer 2020.

The project includes the parking lot improvements at Peace Dale Elementary School.

To learn more about the Peace Dale parking lot project, please download the information sheet below:
PDES Parking Lot Project

Labrynth Information

To view the project updates about the Peace Dale parking lot project, please download the information  below:

PDES Parking Lot Project Summary Update 1 (June 2020)

PDES Parking Lot Summary Update 2 (July 2020)

PDES Parking Lot Summary Update 3 (July 2020)

PDES Parking Lot Summary Update 4 (July 2020)

PDES Parking Lot Summary Update 5 (July 2020)

PDES Parking Lot Summary Update 6 (July 2020)

PDES Parking Lot Summary Update 7 (August 2020)

PDES Parking Lot Summary Update 8 (August 2020)

PDES Parking Lot Summary Update 9 (August 2020)

_________________________________________________

SAFE, SECURE & HEALTHY SCHOOLS: Vestibule Projects
FALL 2019

IMPORTANT UPDATE (as of December 31, 2019): All vestibules are now deemed substantially complete per RI Department of Education.  We are excited to announce that this project was a success.
Presentation of the COMPLETED Vestibule Project

In order to provide safety precautions for our schools, we have determined that security upgrades were needed at a number of our schools.  The project includes front door vestibule hardening and upgraded security systems at South Kingstown High School, Broad Rock Middle School, Peace Dale Elementary School, Wakefield Elementary School, West Kingston Elementary School, and Matunuck Elementary School.  The project also includes the parking lots improvements at Peace Dale Elementary School.

To learn more about each vestibule project, please download the information sheet below:

WKES Vestibule Project
CCMS Vestibule Project
MES Vestibule Project
PDES Vestibule Project
WES Vestibule Project
SKHS Vestibule Project

vestibules